Setting Your Workdays

Customize your project schedules in BuilderPad by defining your workdays. This article explains how to set your company's working days, which will accurately reflect in your project timelines and help in creating realistic and manageable schedules.

Written By Stefan S.

Last updated 7 months ago

Setting up what is considered a workday vs non-work day helps to ensure proper start and end dates for your schedule items.

For example, lets say you have a schedule item that is suppose to take 3 work days and your work days are set to Monday - Friday. If the item was to start on a Friday, it would end on Tuesday of the following week. Friday (Day 1), Monday (Day 2), Tuesday (Day 3).

If you change your work schedule to Monday - Saturday, this example item would be set to complete on Monday. Friday (Day 1), Saturday (Day 2), Monday (Day 3).

Here is how you set your workdays in your account: