Adding Predecessors

Learn how to create dependencies and streamline your project timelines in BuilderPad by adding predecessors to your tasks. This guide explains how to link tasks, set up dependencies, and ensure a logical workflow for your projects, preventing delays and improving overall efficiency.

Written By Stefan S.

Last updated 7 months ago

BuilderPad's schedule utilizes a "Finish-To-Start" dependency by default, due to the nature of construction.

You can also add "Lag days" to create a buffer between tasks.

For example, if you need a two-day delay between the finish of one task and the start of another, you can establish a finish-to-start dependency and specify two days of lag time. You enter lag time as a positive value.

Adding Dependencies from the list view:

Adding Predecessors from the Gantt view: